Project Schedule

The schedule below outlines the five phases of the Orange County Trails Master Plan, including the dates and action items associated with each phase. If you have any questions or need additional assistance, please contact Orange County Parks and Recreation at 407-836-6200 or at parks@ocfl.net.


Research and Analysis | June 2020 to September 2020

The Research and Analysis phase began in June of 2020 and will continue through September of 2020. During this phase the existing trail conditions will be reviewed, the first public outreach event will take place, and an Existing Conditions Summary Report will be created. The list of tasks are listed below:

Existing Trail Conditions

  1. Review Trail Master Plans
  2. Field Reviews
  3. Trails Incidents Analysis
  4. Stakeholder Interviews

Public Outreach #1

  1. Public Kick-off Meeting

Existing Conditions Summary Report

Analysis of Trail Corridors | August 2020 to September 2020

The Analysis of Trail Corridors task began in August of 2020 and will continue through September of 2020. During this phase a trail corridor list will be developed, prioritized, and ranked. The list of tasks are outlined below:

Develop Trail Corridor List

Trail Prioritization Matrix

Tier 1 and Tier 2 Rankings

Trail Feasibility Analysis | September 2020 to November 2020

The Trail Feasibility Analysis phase will begin in September of 2020 and continue through November 2020. During this phase the Tier 1 Concept Plans will be developed, Tier 2 Feasibility Studies will be conducted, and the second public outreach event will take place. The list of tasks are outlined below:

Tier 1 Concept Plans

  1. Written descriptions and graphics of Tier 1 trail concepts

Tier 2 Feasibility Studies

  1. Recommended trail alignment, development phases & funding

Outreach #2

  1. Present recommended trail alignments to the public and seek final input

Develop Trail Design Guidelines | November 2020 to December 2020

The Develop Trail Design Guidelines phase will begin in November of 2020 and continue through December of 2020. During this phase the Trail Corridor List will be developed.

Develop Trail Corridor List

Project Wrap-Up | December 2020 to February 2021

The Project Wrap-Up phase of the project will begin in December of 2020 and continue through February of 2021. During this phase the Master Plan will be drafted and finalized and county and BCC presentations will take place. The list of tasks are outlined below:

Draft Master Plan

County Presentation(s)

Final Master Plan

BCC Presentation

Project Completion